- Riken Yamamoto
The Circle, Zurich
The Circle represents the consistent development of the commercial centres near the airport. After a construction period of around five years, the project by well-known Japanese architect Riken Yamamoto offers its operators an enormous net useful space of 180,000 m2. The massive building is home to a medical centre of the university hospital of Zurich, two hotels, a congress centre as well as attractive offices and spaces for art, culture, gastronomy and education. The majority of useful space has already been leased. The Circle is thus becoming a cultural and economic gem which shines beyond the boundaries of the airport. The project was realised by a co-proprietor cooperative in which Flughafen Zürich AG is invested with 51 percent and Swiss Life AG with 49 percent.
Fire-resistant facades: fire-resistant filigree lift glazing
Blaser Metallbau AG co-created a major part of the interior space. The metal construction company from Andelfingen planned, produced and supplied around 500 m2 of transparent lift glazing, including the stainless steel frames around the lift doors. The technical requirements of the components were rather different to the norm as these interior gates must meet fire protection class E30.
The post-lock front designed for unheated premises consists of a circumferential frame made from 45 mm wide and 110 mm deep steel pipes on the lift side and 45 x 23 mm clear, anodized aluminium cover strips on the hall side, all from the forster thermfix vario system. Due to the fact that the premises are unheated, it was not necessary to implement thermal separation, meaning the glass needed to be just 14 mm thick. Although included in the profile system, the controlled drainage through the system's own drainage system was irrelevant for these interior rooms.
The construction of projects of this magnitude requires entirely different logistics and administration from companies than the construction of ordinary commercial buildings. An online delivery planning tool was used, for instance, in which planned deliveries has to be registered at least three days in advance. The terminal and required lifting equipment, such as crane, etc., also had to be booked well in advance. Deliveries then had to be completed within a timeframe of 15 minutes, or else the deliveries were rejected.
Forster Profilsysteme AG also processed all solution proposals and deliveries of materials required accurately and professionally and complied with them during all construction phases to ensure that the exact deadline requirements could be met.
The Circle – an exciting challenge
"The fact that our lift glazing was spread across three parts of the building with several cores and floors did not make this project any easier," comments Rolf Bechtold. "Even taking the measurements already proved to be a great challenge. In addition to taking the measurements at the brick work, many other factors had to be accounted for and calculated into the planning, such as already installed lifts, pipelines, cable ducts and planned wall and ceiling panels, floor coverings and adjoining doors. In addition to the tough architectural requirements, the many company interfaces and various approval instances also constituted a challenging core aspect during the planning process."
Planning phase
The design plans were prepared gradually by several Hammer designers. The competent advice and system-relevant support from the technical experts at Forster Profilsysteme AG were crucial for the success of this phase. To create a well-planned logistics structure, work preparations, procurement, fabrication, surface treatment, assembly, supplies, transport and installation were planned and triggered just in time.
Production processes
The production processes were also graduated in accordance with logistics planning. The profiles were cut and processed in the company's own processing centre. Welding preparations as well as riveting and welding work were performed in a throughfeed process until the corresponding elements were forwarded to the next processing station for grinding. Once the external surfaces were treated, fittings and seals were installed, the first function and quality checks performed and the elements were placed on the exact pallets, as documented, for transport to the construction site.
Automatic sliding doors – also with swing-out function
In addition to a large number of manual doors, Hammer also produced and delivered various automatic sliding doors with and without swing-out function using the forster fuego light, EI30, profile system. The responsible parties chose Record Türautomation automatic drives.
Doors with swing-out function (with rotating door panel on the sliding panel) are activated with a motion sensor in standard mode and can be accessed normally from both sides through the sliding function. In case of fire, the sliding panels are closed and locked through the fire protection controller. The integrated swing-out escape route function is activated and the integrated revolving door panel can be opened in the direction of the escape route.
Hammer also produced automatic EI30 revolving doors. The forster fuego light profile system was also used for this purpose.
Used systems
Involved stakeholders
Architect
- Riken Yamamoto
Fabricator
- Blaser Metallbau AG, Andelfingen
- Hammer Metall AG, Nänikon
Other stakeholder
- Zurich Airport / Swiss Life (Clients)